|
Gold Hard Hat Award
Coors Golden Distribution Center
Submitted by: Saunders Construction
Inc.
The new 276,000-sq.-ft. Coors Golden Distribution Center,
built by general contractor Saunders Construction, utilizes
Thermomass insulated tilt-up panels and is now the largest
insulated concrete wall panel building in Colorado. The patented
Thermomass insulation system provides a durable and thermally
superior facility - in fact, the introduction of thermally
efficient insulated tilt-up concrete panels could very well
promote wider utilization of this system throughout Colorado.
The Thermomass walls were built in three phases: the first
phase involved forming and casting three-in. concrete "face"
panels on the building's slab on grade. A two-in. rigid insulation
board was then connected to the face using fiber composite
connectors. The final step involved casting an eight-in. structural
concrete panel over the insulation board. Once all of the
elements of the insulated wall panels were in place - creating
a "concrete" sandwich of sorts - the walls were
set.
A 275-ton crawler crane was used to set the building's 121
panels. The largest panel - 45-ft., 6-in. tall by 28-ft.,
6-in. wide - weighed 177,000 lbs. and is the heaviest panel
ever erected in the state.
In addition to setting new tilt-up records, the building's
construction schedule is also worth noting. The entire foundation
system, slab-on-grade and wall panel system were constructed
in just 12 weeks. More than 13,000 cu. yds. of concrete and
over 100,000 sq. ft. of panel were erected in just nine days.
Silver Hard Hat Award
East Cherry Creek Valley Water
and Sanitation District Water Storage Tank
Submitted by: Grimm Construction
The challenge of this project was to design and construct
a 10 million-gal. post-tensioned concrete water storage tank
for East Cherry Valley Water and Sanitation District and put
it into service in 13 months. The district had storage capacity
shortfalls and required the additional capacity for the 2002
water season.
The most significant portion of a post-tensioned concrete
reservoir is construction of the deck, and this task had to
be done during Colorado's cold season. The deck concrete placement
was scheduled for what turned out to be a cold Saturday in
March when two batch plants could be dedicated by LaFarge.
Approximately 100 people turned out that morning to place,
finish, test and engineer the placement of 1,800 cu. yds.
of concrete.
Upon arrival, crews discovered approximately six in. of snow
and ice on top that could have prevented the placement from
happening. Crews attempted to blow the deck off with air compressors,
but the frozen snow remained. The team located a fire hydrant
onsite that was fed by their existing water wells, which come
out of the ground at approximately 80 degrees Fahrenheit.
General contractor Grimm Construction's crews used a fire
hose to melt the snow and ice and warm the rebar and post-tensioning
system so the placement could be accomplished on schedule.
In six hours, the deck was transformed, a section at a time,
from a sheet of white snow and ice into a finished 70,000-sq.-ft.
slab of concrete.
Bronze Hard Hat Award
Waterside Lofts
Submitted by: Etkin Skanska
The 13-story, 164-unit luxury condominium complex, which
fronts Cherry Creek in lower downtown Denver, features high-quality
finishes and three levels of underground parking.
The Waterside lofts structural system consists of a post-tension
slab with a requirement of a Class A finish. The exterior
of the building is made up of field-formed composite metal
panels, brick veneer and exposed concrete columns parged with
EIFS.
The interior units are exposed concrete with concrete balconies
and open metal railings. The 13 stories with three stories
below grade parking requires a full-time dewatering system.
General contractor Etkin Skanska started construction in
November 2000 and completed it in September 2002.
Return
to Best Of 2002 List >>
|