|
Loan OK'd to Speed I-70 Viaduct Repairs/COSMIX
Starts Work at Garden of the Gods
A $5.5 million contingency funding
loan approved by the Colorado Transportation Commission in
October will expedite much-needed repairs on the I-70 viaduct
between Brighton and Colorado boulevards.
I-70 Viaduct Repairs
to Start Soon
The Colorado Transportation Commission agreed in October to provide a $5.5
million contingency funding loan to the Colorado Department
of Transportation's Denver metro region.
The loan will expedite much-needed repairs on the I-70 viaduct
between Brighton Boulevard and Colorado Boulevard and will
be repaid using potential funding sources allocated to the
region.
"The loan will help us move forward with an $8 million
project that will increase the life of this bridge by up to
10 years until we can replace it," said CDOT Regional
Transportation Director Pam Hutton. "This first phase
of the project will allow us to replace expansion joints and
provide temporary shoring. As additional funding becomes available
in the future, we will continue to make further repairs to
the viaduct."
The repairs will include expansion joints, bearing replacement
and drain modifications. Temporary shoring will be included
as part of the bridge work to ensure public safety during
construction.
The total cost of all repairs is estimated to be at least
$30 million.
While CDOT looks for state and federal funding to make additional
viaduct repairs, the environmental impact statement is analyzing
transportation alternatives to improve the I-70 corridor from
I-25 to Tower Road. The study, which should be complete in
2008, will determine if the viaduct should be replaced or
removed altogether.
CDOT estimates that replacement or realignment of the highway
could cost as much as $600 million. CDOT's annual budget is
approximately $800 million, including maintenance and construction.
The first project to repair the I-70 viaduct will be advertised
this December, and construction will begin in February or
March 2006.
COSMIX Starts
Work at Garden of the Gods
Rockrimmon Constructors has begun COSMIX construction work on the ramps at
the Garden of the Gods/Interstate 25 interchange, which will
improve safety and capacity at one of Colorado Springs's busiest
interchanges.
Two ramps - the northbound on-ramp and southbound off-ramp
- will be reconstructed, with work on the northbound ramp
under way first. It is expected to take approximately two
months to complete.
The Garden of the Gods interchange improvements are one of
five optional elements to the COSMIX contract that Rockrimmon
Constructors has committed to completing during the project.
The optional work - called Additional Requested Elements,
or AREs - represents a "wish list" of I-25 work
that the Colorado Department of Transportation could not fit
into the project's fixed budget of $150 million.
Seven optional AREs were included in the request for proposal
that CDOT issued for the COSMIX project in September 2004,
in addition to the required work of widening I-25 to three
lanes in each direction from just south of Bijou Street to
the North Academy Boulevard interchange and reconstruction
of interchanges at Bijou, North Nevada Avenue, Rockrimmon
Boulevard and Corporate Centre Drive.
The AREs do not add any additional cost to the project budget.
Proposals from contractors for the project were judged, in
part, on how many of the seven AREs they committed to doing.
Rockrimmon Constructors committed to completing five AREs,
as well as the entire COSMIX project by the end of 2007, a
year earlier than requested by CDOT. The work at the Garden
of the Gods interchange will add an additional lane to the
northbound on-ramp.
Rockrimmon Constructors will keep one lane open to the public
by phasing this work. The second portion of interchange work
will be on the southbound off-ramp and provide two right and
two left turn lanes onto Garden of the Gods, which will increase
capacity and improve safety. The southbound work may begin
later this year or be delayed until spring 2006, depending
on weather and other factors.
The COSMIX team is currently working with the city of Colorado
Springs and area businesses and residents to find the best
concept for conducting that phase of work. The improvements
to the Garden of the Gods interchange are considered one of
several benefits the Pikes Peak region will gain because of
the design-build approach on COSMIX.
Click
here for more Infrastructure News >>
|