|
ECCV Announces Partners
in Water Pipeline/Major T-REX Work Begins on University Boulevard/Final
Widening Project Resumes on Berthoud Pass
The South Metro Water Supply Authority
will participate in the East Cherry Creek Valley Water and
Sanitation District's planned Northern Pipeline, part of the
H2'06 project that will supply renewable water to the southeast
metro area.
The East Cherry Creek Valley Water and Sanitation
District announced in early spring that the South Metro Water
Supply Authority has agreed to participate in ECCV's Northern
Pipeline.
ECCV's Northern Project includes the Northern Pipeline, pump
stations and a treatment plant to serve its customers' water
needs for the future.
In 2006 the Northern Water Project - named H2'06 - will supply
renewable water to the southeast metro communities that currently
rely on nonrenewable groundwater.
The source of this water is the South Platte River. Water
will be taken from the river near the Adams-Weld County border
and injected into the Beebe Draw, a shallow aquifer system
near Barr Lake.
The addition of new participants in the Northern Project
will allow ECCV to increase the planned pipeline size from
42 in. to 48 in. The SMWSA will pay around $9.5 million total
for its capacity in the pipeline. The overall cost of the
Northern Pipeline is estimated at $67 million.
Major Work Begins on University
Boulevard
Crews installed drainage lines and shifted traffic on University
Boulevard in early April as part of the Transportation Expansion
Project - specifically, the reconstruction of the University
Boulevard/I-25 interchange.
The interchange is being rebuilt as a Single Point Urban
Interchange, replacing the old diamond and cloverlead ramp
configuration. The SPUI will use a single bank of lights under
I-25 to increase traffic flow by providing more time for traffic
to move through the intersection.
The new configuration will be similar to the existing one
at the Santa Fe Drive/Belleview Avenue interchange.
The $1.67 billion T-REX project - approved by voters statewide
- includes highway widening, drainage, bridge and interchange
improvements along 17 miles of I-25 and I-225, and a 19-mile
extension of the region's light rail transit.
CDOT Begins Work on New 120th Avenue Bridge
Over I-25
Construction began the westbound portion of the new 120th
Avenue bridge over Interstate 25 with the installation in
April of 16 concrete box girders.
The bridge work is part of the project that replaces the
120th bridge over the interstate. The new bridge will be approximately
70 ft wider and 50 ft longer than the current bridge. The
additional width allows the bridge to accommodate three through-lanes
and two left turn lanes onto I-15 in each direction of 120th
Avenue.
The project also includes new retaining walls, extends the
acceleration lane from the RTD Park-n-Ride to the southbound
I-25 on-ramp, adds wide sidewalks, replaces the traffic signals
at the on- and off-ramps and improves drainage.
Jalisco International Inc. is the contractor for the $13.2
million project. The 120th Avenue portion will be completed
by November; the entire project will be finished by July 2006.
Final Widening Project Set to Resume on
Berthoud Pass
The second season of work has begun to widen the final two-mile
segment of U.S. 40 on the east side of Berthoud Pass.
This year's construction includes adding a climbing lane
to the existing two-lane highway, shoulder widening, new retaining
walls and grubbing and clearing operations. A large-animal
crossing will also be placed under the highway.
On-road construction will continue through mid-November.
It will be suspended during the Memorial, Independence and
Labor Day weekends. Work that does not impact traffic will
continue during the winter, through mid-April 2006.
Lawrence Construction Co. of Littleton is the contractor
for the $15.6 million project. The entire project is scheduled
for completion in the fall of 2006.
The widening of Berthoud Pass was identified as one of Colorado's
highest priority projects in 1996, when CDOT's transportation
commission established its statewide list of 28 strategic
transportation projects.
I-70 Improvement Project Set to Start in
Georgetown Area
CDOT is replacing concrete median barriers along Interstate
70 on Georgetown Hill.
The operations mark the start of an extensive improvement
project between the Bakerville area and Empire Junction (U.S.
40) that includes rotomilling and asphalt paving, installation
of new guardrails, wire rope safety fencing, bridge rails
and striping. Work will also include replacement of bridge
expansion joints and culvert repairs.
Rotomilling and paving began in mid-May.
Kiewit Western Co. of Littleton is the contractor for the
$5.2 million project, scheduled for completion in September.
Click here for
more Infrastructure News >>
|