|

Outstanding
Engineering Design: Highland Bridge
|
Submitted by Carter & Burgess Inc.
|
Highland Bridge
Denver
Owners: City
and County of Denver, Colorado Department of Transportation,
Regional Transportation District
Engineer: Carter
& Burgess Inc.
Contractor:
Hamon Contractors Inc.
Among the Subcontractors:
Hartwig & Associates, Appius Engineering,
Clanton & Associates
|
The third in a family of three signature pedestrian bridges,
the Highland Bridge unites Denver's Lower Downtown with the
Highland neighborhood across Interstate 25. This final connection
helps the city and county realize its goal of improving the
quality of life for visitors and residents of the Central
Platte Valley by making the environment more pedestrian- and
bike-friendly.
The final design features a dramatic triple-rib steel arch,
rising 70 ft above the ground and spanning 320 ft over I-25
at its maximum. The flared cross-hanger arrangement for the
asymmetric cable stays provides a sweeping support system
for the suspended bridge deck.
The arch design and steel construction details were determined
after input from fabricators and general contractors. The
overhead arch was constructed in four sections and erected
in phases over I-25. The plaza, ramp and abutment designs
were developed with input from stakeholders to reflect the
shared vision of adjacent communities.
Critical to the urban design concept was the creation of
a vertical circulation area to transverse a 13-ft change in
grade from the structure deck down to the existing Platte
Street elevation. The need for long ramp access, in addition
to stair access, drove the design toward an architecturally
sophisticated and urban solution. The refined landscape and
lighting design accentuates both the plaza and structure.
The plaza provides direct access to the Platte Street shops
and Commons Park.
|

Outstanding
Engineering Design: Sonny Lubick
Field at Hughes Stadium Underdrain
|
Submitted by The Engineering Co.
|
Sonny
Lubick Field at Hughes Stadium Underdrain
Fort Collins
Owner: Colorado
State University
Architect:
Aller-Lingle Architects LLC.
Engineer: The
Engineering Co.
General Contractor:
Nemaha Landscape Construction Inc.
|
From previous geologic studies, it was known that the CSU
stadium and its field were constructed over a large expanse
of bedrock. Pockets of the bedrock had been removed, leaving
subsurface ground-water collections. In that state, surface
drainage during snowmelt and rainstorms produced standing
water and a spongy playing field.
To solve the problem, a subsurface drainage system was designed
to collect groundwater and transport it to a central point
at the south end of the field. The architects designed a field
drain to collect surface water runoff that fell onto the field
and convey it to the same central collection point. The storm
sewer system was also redesigned. All these drainage systems
were directed to a new collection manhole where a duplex pump
system moves water to the existing storm drain and where it
exits the stadium.
Because the slope of the new playing field amounts to only
a 3/8-in. drop over 10 ft, the project team needed a precise
method for checking the as-built conditions to get a finished
subgrade tolerance of only 1/8-in. The survey team chose a
combination of GPS//RTK and differential leveling methods,
and surveyors made themselves available on short notice to
perform checks so that no time was lost during an already-tight
schedule.
To complete the new playing field, the subgrade was topped
with synthetic turf that complements the university's synthetic
turf practice field.
|

Outstanding
Engineering Design: McCaslin Boulevard
Pedestrian Bridge
|
Submitted by Parsons Brinckerhoff
|
McCaslin
Boulevard Pedestrian Bridge
Louisville and Superior
Owner: Regional
Transportation District
Architect:
Regional Transportation District
Engineers: Regional
Transportation District, Parsons Brinckerhoff
|
Spanning U.S. Highway 36 between Louisville and Superior,
the McCaslin Boulevard Pedestrian Bridge provides access for
transit passengers to a new RTD park-n-Ride facility and has
become a landmark for local residents. With additional capacity
in the planning stages for the U.S. 36 corridor, CDOT required
that the bridge span the entire width of its right-of-way
without a center pier. A steel basket handle arch was selected
to create an architectural structure that blends with the
Flatirons to the west.
The completed structure spans 234 ft and consists of 20-in.-diameter
pipe tied arches and steel deck framing supported by steel
suspension rods with a concrete deck. The arches were fabricated
in Duluth, Minn., and shipped in four pieces. Complex connections
between them and the deck framing consist of concrete thrust
blocks with a post-tensioned connection of the deck framing
to the thrust block.
|
To minimize road closure, the entire superstructure was erected
in a CDOT right-of-way parallel to U.S. 36 and lifted into
place during one eight-hour, overnight closure. Three cranes
were used. One stationary crane lifted and stabilized the
north bearings, then a second one lifted the south end of
the structure and boomed out over the westbound lanes reaching
to a crawler crane waiting in the eastbound lanes. At this
point the structure was "handed off" to the crawler
crane, which then walked the south end of the structure into
place and lowered it onto the south abutment - eliminating
any destruction to the median and barrier during erection.
Click
here for more Features >>
|