|
(tie)
Outstanding Mechanical/Electrical
Project: Anschutz Inpatient Pavilion
- Phase II
|
Submitted by Trautman & Shreve Inc.
|
Anschutz Inpatient Pavilion
- Phase II
Aurora
Owner: University
of Colorado Hospital
Architect:
HDR Architects Inc.
Engineer:
BCER Engineering Inc.
General Contractor:
Haselden Construction Inc.
Mechanical Contractor:
Trautman & Shreve Inc.
|
The mechanical design and construction teams for the Anschutz
Inpatient Pavilion's second-phase build-out were faced with
serious challenges. First, the hospital's first six levels
are operational, and hospital authorities didn't want the
patients disturbed by construction activity. This meant working
on levels seven through 12 with only minimal access to the
first six.
Second, a new addition was being built adjacent to the existing
building. As such, all materials were crane-lifted and delivered
to the site through windows. This included 30 miles of piping
- the equivalent of 8,000 pieces of pipe, each 20 ft long,
300,000 lbs of ductwork and all of the air flow equipment,
and a mechanical penthouse that contains three massive air
handling units.
Each unit was shipped in eight pieces weighing up to 12,000
lbs each. A section of an exterior penthouse wall was removed
so each piece could be lifted into the mechanical room. Once
each piece was maneuvered into place, the units could be assembled.
Adding to the job's complexity, the entire domestic water
systems were designed to be upgraded to handle the additional
load of the build-out. Because they were built in Canada,
the air-handling units were a long-lead item. In order to
get the seventh level occupied quicker, a temporary air handling
unit was used until the permanent units could be brought online.
The turnover of the domestic water upgrade created another
dilemma. Domestic water piping was not complete on the other
build-out levels, which meant the new system could not run.
To solve this, a temporary domestic water heat exchanger and
pumps were used to supply the lower levels, including level
seven.
The bone-marrow transplant level presented the next challenge
since the area must remain entirely sanitized because its
patients have no immune systems. The team designed and built
a "no bacteria zone" level. Infectious disease control
isolation rooms include fixtures, diffusers and showers that
are specially cleaned, sterile and protected with bio-guard.
Hard rock ceilings were installed so bacteria and germs cannot
penetrate the ceiling. A dedicated air-handling unit and system
was also installed to supply sanitized 99.9 hepa-filtered
air.
|

Outstanding Mechanical/Electrical
Project: Whole Foods Market Distribution
Freezer Warehouse
|
Submitted by Mark Young Construction Inc.
|
Whole
Foods Distribution Freezer Warehouse
Aurora
Owner: Whole
Foods Market
Design-Builder:
Mark Young Construction Inc.
Engineering/Design
Consultants: RAD Engineering, Moyer Engineering,
Dave Willets
Among the Subcontractors:
Mark Young Construction Inc., Wayne's Electric, Kysor
Warren, Metl Span, J.L Hermon & Associates/Recold
|
The design of the 40,000-sq-ft Whole Foods Market freezer
warehouse - the company's main frozen food distribution hub
for the Rocky Mountain region - provides energy savings through
two main approaches. It uses an evaporative water-cooled condenser
instead of air-cooled condensers and the heat rejected by
the refrigeration system to heat the water heaters for the
radiant-floor heat system installed under the concrete slab
and insulation.
The freezer and dock space are built with foam-injected metal
panels and range in heights up to 23 ft, 4 in. The panels
are built within the LEED requirement of 0.65 initial reflectivity
and initial emissivity of 0.90. The foam core contains no
VOCs, and the blowing agent is HCFC-22, which has a low ozone-depleting
potential of 0.05 and is sanctioned for use by the EPA until
2010. The finished panels are completely encapsulated in a
material called "Metl," which prevents the off-gassing
from the blowing agent after panels are shipped and installed
on the building.
Click
here for more Features >>
|