|
The 2003 Colorado Construction Gold
Hard Awards
Outstanding Environmental Project
Gold Hard Hat (tie)
Fossil Trace Golf Course
Submitted by: American Civil
Constructors
Located in Golden, this aggressive new golf course is a
historic site whose excavation turned up five dinosaur tracks
and palm frond fossils on the 12th and 15th greens. As a
result, ACC Golf maintained the integrity and uniqueness
of the site throughout construction, adding a small museum
to the course, with casts of several dinosaur tracks.
ACC preserved a number of existing rock formations and incorporated
them into play throughout the course. Multiple ponds and
waterways were built, including wetlands for the area's
extensive wildlife. ACC moved more than 1.1 million cu yds
of dirt on this challenging course.
Twenty-ft-tall pillars of sandstone emerge from the 12th
fairway, reminding each player of the trace fossils of palm
fronds and triceratops footprints located adjacent the 12th
green.
Since the area is also a former clay mine pit, several massive
relics of clay mining equipment were left in place throughout
the course as a reminder of the rich history of the property.
Because of the history of the site, ACC was tasked with
over-excavating, lining and installing fly ash over the
20-acre landfill portion of the project.
| PROJECT
TEAM |
| Owner: |
City of Golden |
| Architect:
|
James J. Engh |
| General
Contractor: |
American Civil Constructors |
| Cartpath:
|
McCaslin Brothers |
| Surveying:
|
KRW Consulting |
| Sod:
|
Pro Landscape and
Nursery |
| Pond
Liner: |
Colorado Lining |
| Earthwork:
|
Satellite Electric
and Tarco |
Gold Hard Hat (tie)
Sheldon Lake Drainage Improvement
Project
Grimm Construction, The City
of Fort Collins and Sear-Brown
Following the severe flood of 1997, the City of Fort Collins
raised its rainfall criteria, updated its master drainage
plans, and identified a number of new projects - one of
these is the Sheldon Lake Drainage Improvement Project.
The initial purpose was to remove more than 250 structures
from the 100-year floodplain by increasing detention in
the lake and golf course.
Improvements included enhanced water quality in the lake,
habitat structures for game fish, repaved streets, new curbs
and gutters, a signature hole on the golf course, a new
detention pond and an extensive stormwater system under
a major arterial street. Stonework with an artist's touch
added to the appearance of the lake and golf course.
Concrete walks also function as weirs, providing additional
drainage controls.
The most critical challenge on this project was removing
more than 100 years of accumulated sediment at the bottom
of the lake. First, more than 20,000 fish were removed and
relocated. Then after the lake was drained, a two-month
process began to scoop the sediment into 32 dump trucks,
which performed 4,300 hauling trips.
Approximately 54,000 cu yds of material were used to revegetate
a natural area, saving landfill space.
By accurately timing the various critical activities, city
departments saved money by sharing costs and coordinating
construction efforts. Timely construction of the project
- $4.3 million in five months - allowed access to the areas
for the summer season.
The new golf course detention pond required raising a green
and re-constructing three tee boxes. Golfers temporarily
gave up two strokes but now appreciate the new challenges
added to the course. Park visitors are enjoying paddle boats
on a clean lake, new pedestrian and bike paths, and the
view from new stone overlooks on the shore.
| PROJECT
TEAM |
| Owner: |
City of Fort Collins |
| Engineer:
|
Sear-Brown |
| Construction
Manager at Risk Contractor: |
Grimm Construction |
| Subconsultants:
|
EDAW
Terracon Western
Obermeyer Hydro
Miller Ecological Consultants
Ernst Engineering
Water & Earth Technologies
Colorado Resource Management
Colorado Division of Wildlife
Colorado State University
Subcontractors: Bemas Construction
Express Concrete
Leisure Time Associates
Lafarge Western |
Click
here for more Features >>
|